Fast action was needed. In close cooperation SANDVIK and the licensor developed a solution. The result - within just ten weeks, Sandvik had delivered 12 tons of super-duplex tubes (Sandvik SAF 2507) and proved the effectiveness of its express delivery program for duplex steels.
Besides major precautions when operating a plant unexpected material failures cannot be ruled out completely. In the case of the Egyptian plant, Sandvik says it was able to make a difference because of its extensive expertise in producing and testing seamless stainless steel tubes, its high delivery flexibility and its long-term and trusting relationship with the licensor.
t: +49 211 50 27 342
e: tubesales-de.smt@sandvik.com
Click here for the full unedited version of the release as provided by the company

Late in 2014 the technicians of an Egyptian Propane Dehydrogenation plant had to face the truth - several heat exchangers had failed unexpectedly and caused a production shut-down.